BOWLER SITE

Dog Off Leash Area Proposal
Preliminary Cost Estimates for Park Facilities Construction

Minimum Requirement Cost Estimates:

Fencing (post & 3 rail & wire) $9/ lineal foot

X

1450 Lineal feet $ 13,050
Double gate system                      $ 900

X

1 $     900
Parking lot (rough est. per space)  $1,500

X

8-10 spaces/ approach road $ 18,000
Garbage Can Receptacles             $ 300

X

4 $   1,200
Picnic Tables                                $ 900

X

2 $   2,700
Benches                                        $ 800

X

3 $   2,400
Porta-potty toilets (monthly cost)   $ 225

X

1 $    225    
Drinking Fountain                         $ 2,500

X

1 $   2,500
Signage (per park)                        $ 2,500

X

1 $   2,500
Minimum Facility Cost Estimates $ 43,475

Park Land Development Cost Estimates (generic preliminary estimates):

Pump Station (lump sum)                 $ 40,000 $ 40,000
Irrigation (per acre)                         $ 15,000

X

3 $ 45,000
Grading (per acre)                           $  3,500

X

3 $ 10,500
Turf (seed/ acre) $ 6,500 (sod/acre) $ 11,000

X

3 $ 19,500
Drainage ave. neighborhood park (est. lump sum)

$   7,500
Engineering ave. neighborhood park (est. lump sum) $  10,000
Park Land Development Cost Estimates $132,500

TOTAL MINIMUM REQUIREMENTS & 
PARK LAND DEV. COST ESTIMATES $175,975

note: Utilities costs can vary greatly depending on the site and conditions, but must be considered. These costs include water, power, sewer & telephone service & irrigation water pond.